Colorado Bulletin No.: CO-300-10-01
DATE: October 20,
2009
SUBJECT: LTP – Conservation Security Program
(CSP) Audit – Deadline for Corrective Actions
TO: All Area
Conservationists
All Area Resource Conservationists
for Programs
All District Conservationists with
CSP Responsibilities
PURPOSE:
To remind offices of the Colorado deadline for corrective
actions identified as a result of the CSP Audit conducted earlier
this year
EXPIRATION DATE: September 30, 2010
ACTION REQUIRED BY:
November 6, 2009
As a result of an agreement between the Natural Resources Conservation Service
(NRCS) and the USDA Office of Inspector General, all active CSP contracts were
reviewed by the end of Fiscal Year (FY) 2009.
Completed “Audit Checklists” were uploaded to the national CSP SharePoint site:
https://nrcs.sc.egov.usda.gov/programs/cspaudit/default.aspx.
Some of these checklists had a “No” answer on one or more of the 23 questions,
and, therefore, required corrective action. Colorado Bulletin No. 300-09-07,
issued May 4, 2009, set a deadline for completing corrective actions
no later than November 6, 2009.
Important points:
- Contracts needing corrective action are NOT to have FY 2010 payments approved until the corrective actions have been completed.
- Any contract that was active in FY 2009 and was audited is subject to the corrective actions, even if the contract expired on September 30, 2009.
- The State Conservationist must certify that all corrective actions have been completed.
Please contact Gary Finstad, Easements Coordinator, at (720) 544-2820, if you
have any questions.
/s/
ALLEN GREEN
State Conservationist
cc:
Tim Carney, Assistant State Conservationist for Programs, NRCS, Lakewood, CO
Ila Binard, State Administrative Officer, NRCS, Lakewood, CO
Gary Finstad, Easements Coordinator, NRCS, Lakewood, CO
Marta Villano, Program Analyst, NRCS, Lakewood, CO
Jon Wicke, Acting Resource Conservationist, NRCS, Lakewood, CO
DIST: O
< Back to Colorado Bulletins
|